
The Scheme aims to alleviate traffic issues through
Lyminster Village with the northern section of the bypass
completing the link road from the A27 at Crossbush, providing
access to Littlehampton.
The progress made in the last six months:
North of Ancient Hedgerow
In the second phase of culvert installation, a
concrete culvert was built to support the live road over the
stream, with a traffic island added for pedestrians and cyclists.
In December, a 250-ton crane removed temporary sheet
piles that had been holding back earth. Additionally, brickwork
was added to the culvert's exterior to enhance its appearance and
provide protection.
Ancient Hedgerow to
Bridleway
Traffic was diverted onto a short section of the new
road for culvert installation, this is over the link road that
will connect the Bypass to the old Lyminster Road. To reduce the
future noise pollution, acoustic fencing has been set up around
the link road.
In landscaping areas, the ground has been prepared,
and hedging whips were planted to promote biodiversity and
establish new hedge lines around the project site.
Bridleway to Black
Ditch
The embankment for the road is awaiting the final
road surface. The footpath on the eastern side is complete, with
concrete borders and marked edges. Pre-cast concrete drainage
units have been installed to direct water runoff into the
drainage system.
Additionally, the farmer's access track has been
finished, with concrete edgings placed around its perimeter to
define its boundaries clearly.
|
South of Black Ditch
In the viaduct's footpath, a subsurface drainage
system (pipes and ditches that run beneath the surface) has been
installed for managing rainwater and preventing waterlogging.
Concrete has also been added along the bridge's
edges in preparation for a new layer of tarmac, ensuring the
pathway will be strong and durable.
|
Significant work is underway to deliver on the
commitments set out in our BSIP. The improvements will
deliver reduced bus journey times, improved passenger information
and upgrades to roadside infrastructure, making bus journeys
easier for passengers. Progress on our capital commitments
are as follows:
- Real time
passenger information (RTPI) screens – A countywide
rollout of RTPI upgrades at bus stops started in January
2024 with 390 having been complete to date and a further 43
planned by March 2025.
- Manor Royal,
Crawley: The final phase of the Manor Royal Highways Improvements,
Crawley will extend the eastbound bus lane on
Manor Royal Road. Construction started in Early February
2025 and is expected to complete in Autumn 2025.
- Bus stop
improvements – A countywide upgrade of bus stops
started in 2024 with improvements made to 43 bus stops and a
further 25 planned by April 2025.
- Bus priority
at traffic signals – The traffic light junction upgrades
started in November 2023 with seventeen having been complete
to date and a further seven planned by March 2025.
- Fastway,
Crawley – Bus stop upgrades have been completed
on 33 bus stops across Fastway Bus Routes 10 & 20.
Further improvements are planned to improve bus journey
times at 3 sites during Spring 2025.
- Western
Boulevard, Crawley – Delivering dedicated bus lanes on the
Boulevard (west) and bus priority upgrades at signalised
junctions nearby. The work was led by Crawley Borough
Council, and the delivery of the project has now been
completed.
- Route 500 Bus
Shelter Scheme –The tendering process is underway for the
installation of 10 shelters along the route. Barnham and
Eastergate Parish Council is leading on this with purchase
of shelters, licencing and installation being project
managed by the chosen contractor.
|
The scheme will deliver a new 4.34km road to the east
of Eastergate, Westergate and Woodgate villages in two phases:
Phase 1 (north): From the A29 south of Eastergate Lane to a new
junction with Barnham Road. Video link here
Phase 2 (south): From Barnham Road to a new junction on the A29 south
of Lidsey bends
Phase 1 update:Following demolition of the Fleurie Nursery site last
Summer, WSCC has continued to work with landowners alongside the
Barnham Road Roundabout site.
WSCC is currently moving forward with the early
construction of the Barnham Road Roundabout (Phase 1A) which will
provide access to some housing and a Primary School site through
the southern route.
The Major Projects team is working with its
specialists to issue a tender for the roundabout's construction and
expecting a Key Decision soon. The tendering process is scheduled
for spring and summer 2025. With subject to land agreements,
construction is anticipated to begin in autumn 2025 and will last
approximately a year.
The scheme emerged from the Haywards Heath Town Study
2015 and aims to discourage traffic through the shopping area along
with providing an environmental enhancement.
Following the public engagement in summer 2022, the
scheme was costed, and funding opportunities were reviewed. The
prospect of additional funding from Central Government is no longer
looking to be viable within the foreseeable future. As such, the
scope of the scheme is being reviewed if it is deliverable using
available developer Section 106 contributions.
ThroughoutSpring 2025,wewill be engagingwiththepublictolearnabouttheirviewsofourproposedplan.
Worthing
Railway Approach and Cross Street
Works to the
Worthing Railway Station frontage and Railway Approach completed
before Christmas, with the exception of minor snagging. The
Railway Approach project, delivered by the Worthing Growth
Programme, was delivered in synergy with the Active Travel funded
Cross Street works to reduce disruption. The project enhanced
accessibility features, increased greening and introduced safety
measures such as improved lighting and CCTV. Additionally, the
project promotes walking and cycling with measures including a
contraflow cycle lane and raised tables introduced.
WSCC also commissioned Artyface to work with the
local community to create four mosaic roundels for the front of
the station with support from local ceramics artist, Alice Mara.
For more information on the mosaic roundels, please click the link.
|
Sustainability was a priority throughout design and
construction with the project’s focus being to create a safe and
attractive gateway between the public transport hub and the town
centre for pedestrians and cyclists. Local contractor Landbuild
were able to reuse a significant quantity of materials within the
project itself or along Bognor Regis Esplanade, as well as
introducing 17 more trees and further planting into the
landscape. A deep dive into the project’s sustainability
attributes will be included in a press release next month
following the project’s opening.
A video flythrough of the completed works is now
available on this link.
|
This scheme aims to enhance active travel, bus
priority measures as well as highway capacity at various
locations along the A259 Bognor Regis to Littlehampton corridor
between Comet Corner and Bridge Road roundabout. We are currently
awaiting for the approval of the outline business case by the
Department for Transport. When approved, a full business case
will be prepared and submitted for further approval before
construction can start.
|
Chichester
City Centre Public Realm Improvements
This project seeks to upgrade and improve the City
Centre experience by resurfacing/re-paving and extending the
pedestrianised areas of North and East Street, with the addition
of new street furniture and planting. Additionally the project
includes the upgrade of mobile and broadband internet
infrastructure.
Initial design concepts were drawn up last year and
were subject to a public consultation which took place in
November 2024.
Over 600 responses were received, which will be used
by the design team to influence the design stage.
We have recently appointed a designer and
commissioned a full site survey.
We are currently:
- Locating and
surveying the position of underground pipes and cables.
- Researching various surfacing options.
- Considering options for the digital
apparatus.
- Working with
telecoms companies to establish who would be interested in
partnering with us for the digital element of the project.
The scheme is subject to funding being secured
before any works can commence.
|
Bognor
Regis Esplanade
As part of the Arun Growth Programme, the project will
improve areas of the public realm by, increasing accessibility,
reducing the speed limit to 20mph, increasing greening and
introducing raised crossings. This will complement wider
improvements in the area including works to place at:
- Place
St Maur (completed)
- Alexandra Theatre
- Bognor Regis Arcade
- The new Premier Inn
hotel
The project is currently under
construction and is
expected to complete in early spring 2025.

Produced by the Stakeholder and Partnerships Officer,
Highways Transport and Planning. Please contact active.communities@westsussex.gov.uk with
any comments or suggestions.
|